Quarterly and Annual Reports

2026 budget plan and guidance on interpreting reports
Shahrisabz City Council decision No. VII-19-140-4-209-K/25 of 30 December 2025 approved local budget revenue and expenditure of UZS 117.04 billion for 2026. This is a full-year plan and must not be treated as nine-month actual revenue or a nine-month plan.
Previously published periodic reports are retained below. Revenue, employment and infrastructure figures should be compared using the same reporting period, units and calculation basis. An approved correction resolving certain differences between totals and component figures in the original report has not been published on this page. Those figures are not presented as fully reconciled final statistics.
Lex.uz — VII-19-140-4-209-K/25
Shakhrisabz development results for the first nine months of 2026
A summary based on the report provided by the city administration. January–September results, progress at the time the report was prepared and year-end targets are presented separately.
January–September results
The volume of services reached UZS 1.316 trillion, with a growth rate of 129%. The city received 410,300 tourists, including 308,200 domestic and 102,100 international visitors. Tourism services amounted to UZS 240 billion, accounting for 18.2% of total services.
Local budget revenue totalled UZS 108.9 billion against a target of UZS 91.4 billion. The report states that the target was met at 119%.
Employment support reached 6,686 women: 1,047 obtained permanent jobs, the employment of 1,410 was formalised, and income improvement measures covered 4,229.
Progress at the time of reporting
USD 73 million in foreign direct investment had been utilised. A total of 31 regional investment projects worth UZS 695 billion had been implemented, creating 1,084 jobs. Small and medium-sized businesses received UZS 368.7 billion in loans.
Under the investment programme, UZS 29 billion funded a new school, additional buildings at four schools and two new kindergartens, all brought into operation. In seven neighbourhoods, 43 km of water supply networks were laid and five artesian wells drilled. A 1.2 km pressure sewer and one sewage pumping station were built in the Sinabog small industrial zone.
A USD 15 million project by Lazzat Pishloq created 85 jobs, while a USD 10 million project by Anxor Kesh LLC created 30. The number of hotels reached 70, with 1,020 accommodation places.
Ongoing projects and year-end targets
A project covering 80 km of water supply networks across 13 neighbourhoods is under way. It aims to increase centralised water supply coverage from 70% to 82% and improve supply for 29,523 residents in 6,039 households.
A project supported by the French Development Agency provides for the construction and reconstruction of six sewage pumping stations and 366.5 km of networks. Sewerage coverage is intended to rise from 14% to 86%. Year-end targets include commissioning 690 apartments in 17 apartment buildings, bringing foreign investment to USD 118 million and tourist arrivals to 600,000.
Source: the city administration’s report, “Доклад финиш.docx”. This page presents a summary. Planned figures are targets and must not be interpreted as completed results.
First quarter of 2026 — service sector statistics
According to preliminary data published by the Kashkadarya Regional Statistics Department on 28 April 2026, the value of market services provided in Shakhrisabz in January–March was UZS 379.8 billion, accounting for 2.7% of the regional total, with a growth rate of 124.0% compared with the same period of the previous year.
Official statistics — PDF, Shakhrisabz city row on page 2
This is a service sector statistical indicator, presented separately from the administration’s quarterly activity report covering all areas.
Key socio-economic indicators
The following figures are taken from the official reports published on this page. The periods differ: 2025 covers the full year, while 2026 covers January–August. No direct growth percentage has been calculated between them.
| Indicator | 2025 year-end results | January–August 2026 |
|---|---|---|
| Industrial output | UZS 856.4 billion | UZS 696.6 billion |
| Volume of services | UZS 1,586.8 billion | UZS 1,125 billion |
| Construction work | UZS 629.8 billion | UZS 552.1 billion |
| Retail trade | UZS 2,476.6 billion | UZS 1,936.2 billion |
| New businesses | 849 | 954 |
The reports give industrial production growth rates of 105.2% for 2025 and 112.3% for January–August 2026. Each indicator relates to its respective reporting period.
January–August 2026 report — PDF·2025 year-end report — PDF
QUARTERLY AND ANNUAL REPORTS OF SHAKHRISABZ CITY ADMINISTRATION
This section publishes quarterly and annual reports on Shakhrisabz’s socio-economic development, investment, industry and entrepreneurship, employment, construction, infrastructure and work carried out in social sectors.
The reports present the area’s key socio-economic indicators, trends, completed projects and results achieved.
SOCIO-ECONOMIC DEVELOPMENT INDICATORS FOR SHAKHRISABZ, JANUARY–AUGUST 2026
SOCIO-ECONOMIC DEVELOPMENT INDICATORS FOR SHAKHRISABZ, 2025 YEAR-END RESULTS