Prospects for the Application of RCC Technology in Hydropower Projects Discussed
2026-11-17 19:25:00 / News

On November 17, 2026, the first meeting of the Scientific Expert Group was held at the Agency for Innovative Development. The Group is tasked with facilitating the identification of technical solutions for investment projects in the hydropower sector based on scientific approaches and supporting their practical implementation.
The meeting was attended by B. Amirsaidov, First Deputy Chairman of the Management Board and Chief Engineer of JSC "Uzbekhydroenergo", as well as Chairperson of the Scientific Expert Group; relevant sector specialists; representatives of research and design organizations; and U. Tashkenbayev, Adviser to the Director of the Agency for Innovative Development.
The meeting focused on the possibilities of applying Roller-Compacted Concrete (RCC) technology in the construction of new hydropower plants, international experience in its application, and its technical and economic advantages.
Experts presented the potential of RCC technology to reduce construction timelines, optimize concrete and cement consumption, and mechanize construction processes. At the same time, particular attention was given to engineering and geological conditions, seismic safety, and ensuring the strength and impermeability of concrete when applying this technology.
In addition, using the Nizhne-Chatkalskaya Hydropower Plant project as an example, the possibilities of combining RCC technology with conventional vibrated concrete (CVC) technology were considered. Information was also presented on the implementation of instrumentation and an automated diagnostic and monitoring system at the dam of the Kuuyi-Chatkal Hydropower Plant.
Following the meeting, the application of RCC technology in new hydropower plant projects was identified as a promising area. JSC "Uzbekhydroenergo" and JSC "Gidroproyekt" were tasked with preparing analytical materials to examine the feasibility of applying this technology and the technical solutions required for its implementation.
These efforts are aimed at expanding the application of scientific approaches in the hydropower sector, introducing advanced international practices, and enhancing the efficiency and safety of investment projects.