An Early Warning System for Mudflows and Floods to Be Introduced on the Maylisoy River
2026-10-20 12:40:00 / News

Andijan Region is among the areas exposed to an elevated risk of mudflows and flooding during the spring and summer months. In particular, sudden increases in water discharge in the Maylisoy River, which flows from the territory of Kyrgyzstan, pose a threat to residents living along its banks in Pakhtaabad and Izboskan districts.
To address this risk, plans are underway to introduce a modern early warning system to alert local communities in advance of potential mudflows and floods on the Maylisoy River. The initiative will be implemented under programmes of the Global Green Growth Institute (GGGI) and the International Water Management Institute (IWMI), in cooperation with the National Committee on Ecology and Climate Change of Uzbekistan, Uzhydromet, the Ministry of Emergency Situations and the Ministry of Water Resources. The programme is funded by the Republic of Korea.
As part of the project entitled “Assessment of Flood and Mudflow Risks along the Maylisuv River Corridor,” Uzhydromet proposed five locations in Fergana and Andijan regions for consideration. Following an assessment of hazard levels, equipment installation opportunities, communications and electricity availability, specialists selected the Maylisoy river system as the primary project site.
Historical records indicate that mudflows occurred on the Maylisoy River in 1958 and 1959, while floods were recorded in 1998, 2010 and 2012. These events caused damage to residential properties, agricultural land and local infrastructure. Accordingly, before introducing the new system, particular attention is being paid to a comprehensive assessment of local hazards, community preparedness for emergencies and existing challenges.
For this purpose, IWMI specialists conducted preliminary assessments and consultations with relevant organisations. On 17–18 September of the current year, representatives of the institute met with officials from the Andijan Regional Hokimiyat, the Naryn-Karadarya Basin Administration, regional emergency management, environmental and hydrometeorological departments, the Karadarya–Maylisoy irrigation system, and the Kuykulok hydraulic facility.
The specialists also met residents of three mahallas located along the river: Qurg‘oncha and Toshqurg‘on in Pakhtaabad District, and Uzunko‘cha in Izboskan District. These communities are home to approximately 12,000 people.
Discussions with residents revealed that access to timely and accurate information about water levels and flood risks on the Maylisoy remains limited. According to residents, there is currently no dedicated system providing regular alerts specifically about conditions on this river. In some cases, people have learned about rising water levels through personal contacts living on the Kyrgyz side of the river.
The assessments also found that some houses in the Uzunko‘cha mahalla are situated very close to the riverbank. In 2010 and 2018, rising water levels caused water to enter the yards of several homes.
Meanwhile, district and regional authorities, together with the relevant organisations, are implementing preventive measures to reduce mudflow and flood risks and prevent potential emergencies. Specialists emphasise that these efforts need to be strengthened further and that mechanisms for protecting local communities must be improved.
The consultations also highlighted the river’s importance to local livelihoods. According to Gulomjon G‘aniyev, a retired worker living in the Toshqurg‘on mahalla of Pakhtaabad District, the river may pose a threat during spring, but its water is essential in summer for irrigating residents’ and farmers’ agricultural land.
Residents and water management specialists put forward several proposals, including reinforcing riverbanks near residential areas, conducting a comprehensive assessment of the section of the river within Uzbekistan, and automating the gates of the hydraulic facility.
According to specialists, installing early warning equipment alone will not be sufficient. An integrated system is needed to ensure that alerts are transmitted promptly from river monitoring points to district emergency management offices, mahalla administrations and individual households.
Other proposed measures include establishing community warning points, developing evacuation plans for each mahalla and conducting practical emergency drills every year before the high-risk spring season. Particular attention should be given to women, older people and families in need of social support.
The project also envisages installing a video camera for continuous, round-the-clock river monitoring and a radar sensor to measure water levels.
Project initiators are currently conducting community surveys and gathering residents’ views and suggestions. At the next stage, risk maps will be developed in cooperation with local communities. By the end of the year, maps identifying at-risk homes, schools and roads, along with evacuation routes and public warning procedures, are expected to be prepared and submitted to the responsible organisations.
The preliminary findings of the assessments and preparatory work are expected to be presented at a seminar in Andijan at the end of the current month.
According to specialists, the experience gained from implementing the system on the Maylisoy River could subsequently be applied to other rivers and streams across the Fergana Valley. The main objective is to notify residents of potential mudflows and floods in a timely manner, allowing them to take protective measures and evacuate to safer locations when necessary.
Reducing the risks associated with mudflows and floods requires coordinated efforts by government agencies, local communities and individual citizens. In this regard, the “Assessment of Flood and Mudflow Risks along the Maylisuv River Corridor” project represents an important initiative to strengthen public safety and minimise the impacts of natural disasters.